Client / Location
 Dean Warehouse, Inc. / East Providence, RI
Services Provided
Closure assessment
Leachate/infiltration control
Regulatory negotiation
Cap analysis
Cap reshaping & grading design
During an environmental assessment of the property, a former gypsum waste disposal landfill (without a liner or leachate control) was discovered. Area surface water runoff had infiltrated the base of the fill, creating a natural subterranean stream.
Closure was ordered by RIDEM under the RI Solid Waste and Wetlands Regulations. Resource Controls performed subsurface characterization by analyzing historical data and concluded that the fill material was not hazardous and that groundwater had not been impacted.
Resource Controls prepared a Site Investigation Report, conducted extensive negotiations with RIDEM, and performed land survey and engineering evaluations to fully define and evaluate alternatives for mitigation activities. Options analyzed include complete removal of the fill material, possibly for beneficial reuse, diversion or enclosure of the subterranean stream inside a culvert and construction of a retention basin to control downstream transport of sediment. |
Project Duration
 2002 - On-going
Project Value
 $200,000
Reference
 Mr. Brad Dean (401) 334-4400
|